How Do I Get Building Approval in Ogun State?
Introduction
How do I get building approval in Ogun State? This is one of the most important questions any property owner, developer, or investor must ask before starting construction. Whether you are building a family home in Arepo, a commercial plaza in Abeokuta, or an industrial facility in Sagamu, securing proper approval from the Ogun State government is not just a legal requirement but also a safeguard against demolition, fines, or future disputes.
In this comprehensive guide, we will take you through the step-by-step process of obtaining building approval in Ogun State—covering the required documents, agencies involved, legal frameworks, fees, timelines, and common mistakes to avoid. By the end, you will have a crystal-clear understanding of how to navigate the system, protect your investment, and build confidently without fear of government intervention.
Understanding Building Approval in Ogun State
Building approval is the official authorization granted by the Ogun State Government through its Ministry of Physical Planning and Urban Development (MPPUD). This approval certifies that your proposed building complies with land use laws, environmental regulations, and physical planning standards. Without it, your building project is considered illegal, even if you legally own the land.
In Ogun State, the planning system is guided by the Urban and Regional Planning Law and the Nigerian Land Use Act, which vests land in state governors. The approval process ensures that development is orderly, environmentally friendly, and in line with the Ogun State master plan.
Many investors and developers wrongly assume that once they have purchased land and obtained a Deed of Assignment, C of O, or Governor’s Consent, they can immediately begin building. However, this is a mistake. Building approval is a separate and mandatory step that validates your architectural drawings, ensures safety standards, and confirms compliance with zoning regulations.
Why Building Approval Matters
Legality of Construction – Without approval, your building risks demolition.
Safety – Approval ensures compliance with engineering and structural standards.
Property Value – Approved buildings are more attractive to buyers, banks, and investors.
Access to Utilities – Utility companies often require proof of approval before connecting water, power, or sewage.
Dispute Protection – It provides legal backing against community or government disputes.
Imagine spending millions to build a luxury duplex in Mowe only for the government to declare it illegal because you skipped approval. This scenario happens often, which is why due diligence is critical.
Step-by-Step Guide to Getting Building Approval in Ogun State
Step 1: Acquire Legitimate Land Title
Before applying for approval, ensure that your land has a valid title such as a C of O, Governor’s Consent, or Deed of Assignment. The state government will not process applications on land under acquisition, green zones, or unauthorized estates.
Step 2: Engage Professionals
You will need a team of certified professionals to prepare your documents, including:
An Architect (for building drawings)
A Surveyor (for land survey plan)
A Town Planner (for planning drawings)
A Structural Engineer (for structural designs)
Using quacks is risky. The Ogun State MPPUD cross-checks and validates signatures of registered professionals.
Step 3: Prepare Your Documents
The following documents are generally required:
Application form (purchased at MPPUD)
Architectural drawings (floor plans, elevations, sections)
Structural drawings (foundation, beams, columns, roofing)
Site plan (showing the position of the building on the land)
Survey plan
Title documents (C of O, Governor’s Consent, or equivalent)
Tax clearance certificate
Environmental Impact Assessment (for large projects)
Step 4: Submit to the Ministry
Applications are submitted to the Ogun State Ministry of Physical Planning and Urban Development at Abeokuta or through zonal offices (e.g., Ifo, Sagamu, Ota). Some LGAs also have liaison offices.
Step 5: Site Inspection
Officials will visit your site to confirm that your documents match the reality of the land. They check boundaries, topography, and ensure no encroachment on government-acquired land.
Step 6: Assessment and Payment of Fees
Approval attracts fees such as:
Processing fee
Building plan assessment fee
Infrastructure development levy
Inspection fees
Fees depend on project size and location. For example, a bungalow in a semi-urban area may cost less than a multi-storey building in Abeokuta.
Step 7: Approval Issuance
Once all conditions are met, the Ministry issues a Building Plan Approval Certificate, signed and stamped. This document is your legal backing to commence construction.
Common Mistakes to Avoid
Starting construction before approval.
Submitting incomplete documents.
Using unregistered professionals.
Failing to obtain tax clearance.
Building on government-acquired land.
Timeline for Building Approval
On average, the process can take 4–12 weeks, depending on:
Completeness of documents
Complexity of project
Workload at the Ministry
Whether clarifications or corrections are needed
Applicants can speed up approval by ensuring accuracy of documents and prompt payment of fees.
Case Study: Building Approval in Arepo
Mr. Ade purchased a half-plot in Arepo and wanted to build a 5-bedroom duplex. He engaged an architect and surveyor, prepared his documents, and submitted them to the MPPUD zonal office. After inspection, he paid ₦650,000 in fees. His approval was issued within 8 weeks. Today, his property is legally recognized, and he enjoys peace of mind.
Contrast this with Mrs. K, who began construction in Ota without approval. Midway through, officials marked her building “REMOVE.” She eventually paid heavy fines and spent an additional 6 months regularizing her approval.
Role of Professionals in the Approval Process
In Ogun State, the role of professionals cannot be overemphasized. The government ensures that only certified experts are allowed to sign and submit building plans. This protects the state from substandard structures and building collapse incidents.
Always verify the credentials of the professionals you hire. Registered town planners, architects, and engineers have unique stamps or registration numbers recognized by the government.
Legal Framework
The legal basis for building approvals in Ogun State includes:
The Land Use Act 1978 (vesting land in the Governor)
The Urban and Regional Planning Law of Ogun State
Relevant environmental and safety regulations
These laws empower the Ministry to regulate, approve, or demolish structures.
Frequently Asked Questions (FAQ)
Q1: Can I build first and process approval later?
A: No. This is illegal and risky. The government may penalize or demolish the structure.
Q2: How much does building approval cost in Ogun State?
A: Costs vary depending on location and building type. For a bungalow, it may range from ₦200,000–₦800,000. For larger projects, costs can run into millions.
Q3: Can I process approval myself without an architect?
A: No. Architectural drawings must be stamped by a licensed architect or professional.
Q4: How long does it take to get approval?
A: Typically, 4–12 weeks if documents are complete.
Q5: What happens if I ignore building approval?
A: Your property may be sealed, marked for demolition, or attract heavy fines.
Conclusion
Getting building approval in Ogun State is not an option—it is a necessity. From securing proper land title to engaging professionals, preparing accurate documents, paying fees, and obtaining the official approval certificate, each step protects your investment and ensures peace of mind.
Whether you are a diaspora investor planning a project in Ogun, a first-time homeowner in Arepo, or a developer in Abeokuta, understanding and following the process will save you time, money, and stress.
If you need professional assistance, our law firm specializes in property documentation, building approvals, title verification, and real estate compliance in Ogun State and beyond. Contact us today to ensure your building project is fully protected.
Contact Us
📞 0806 555 3671, 08096888818, 08024200080
📍 Chaman Law Firm 115, Obafemi Awolowo Way,Allen Junction, Beside Lagos Airport Hotel, Ikeja, Lagos
👉 Book a consultation now: www.chamanlawfirm.com/book-consultation
Chaman Law Firm – Your Right, We Protect